TL;DR
Emails released under freedom of information show Scottish Development International, the overseas arm of Scottish Enterprise, asked in June 2024 for talks between ILI Group, a Hamilton developer, and an unnamed data centre company to stay private “pending an NDA”. The Ferret reported the emails on 25 November, nine days after news that West Lothian Council had agreed its own NDA with an undisclosed data centre company.
What the emails show
The unnamed firm had enquired in 2024 about Scotland as a data centre location, and SDI hosted it twice on tours of possible sites. On 20 June that year, the day after the introduction, an SDI official wrote that they would be “grateful if we could keep this engagement private pending an NDA if there’s common ground”. About half an hour after that, an email headed “NDA- ILI signed” went round with the agreement attached. The two firms had started discussing the NDA the previous day.
Scottish Enterprise withheld the company’s identity on grounds of commercial confidentiality. It says it did not sign the NDA, that the agreement was “proposed by and agreed directly between these businesses, without our involvement”, and that the opportunity “ultimately did not progress”. The Scottish Government called confidentiality steps “standard practice, regardless of the sector”.
Why the operator matters
The Ferret’s request was meant to find out which companies might end up running Scotland’s data centres. Local developers such as ILI often take projects through planning, then sell or lease them to an operator once permission and a grid connection are secured. ILI’s spokesperson said NDAs are normal in early commercial talks and do not limit what planners or communities can see.
Critics disagree. Patrick Harvie, who previously led the Scottish Greens, said the agency should “under no circumstances be encouraging a data centre developer to sign a secretive legal agreement”. Duncan Dunlop, a Lib Dem MSP for the south of Scotland, said communities are being asked to comment with “no idea about who will own and operate” the sites. Kim Pratt of Friends of the Earth Scotland went further, arguing that the country should hold a public consultation on whether it wants AI data centres at all.
Looking forward
The disclosure follows West Lothian Council’s NDA with an unnamed data centre firm, which The National reported on 16 November, and our earlier report on data centre lobbying at Holyrood. The Ferret has a second FoI outstanding on an “active” operator enquiry that Scottish Enterprise disclosed in September. In our view, the identity of eventual operators is a pressure point for Scottish planning: residents are asked to judge projects whose end users stay hidden, and SDI’s request shows a public agency also favouring privacy in early talks.