TL;DR

CX Tech’s plan for a £16.5bn data centre at the former Chapelcross nuclear site near Annan has produced more than 10,000 representations, the largest number Dumfries and Galloway Council’s planning department has ever received, BBC News reported on 18 November. The last period for comments ends on 29 November. Officers will then finish checking the submissions before any decision is taken.

How the council is handling the volume

The council had already said it could not post every comment online, as it would normally do. Instead it will publish the number of representations for and against, the names of those who made them and a summary of the planning grounds raised, and it has promised to do so “well ahead” of a decision. It thanked residents for their patience while the work is done.

The application, lodged in September, seeks planning permission in principle. The developer says the site could support up to 750 construction jobs and about 540 permanent posts, plus hundreds more indirectly, and has called it a “once-in-a-generation opportunity” for the region. Campaigners dispute those job figures and cite fears over household energy bills, strain on the grid and the industrialisation of a rural area. Kim Cairns, who campaigns against the scheme, called it a “monstrosity on the environment”.

The national picture

The record count lands in a week of wider resistance. Thousands marched in Edinburgh against Scotland’s AI data centre plans over the weekend of 14 and 15 November, and the BBC says fresh planning guidance from the Scottish government will be published soon.

The grid is the other constraint. Northeastern Global News reports that the UK government expects Britain to need data centres drawing up to 6 gigawatts at full power, against around 2.4 gigawatts of capacity today. Waleed Iqbal, a data science academic at Northeastern University London, told the outlet that power, rather than land, is the main obstacle to that target. The outlet adds that some proposed sites could wait close to ten years to be connected to the National Grid.

Looking forward

The 29 November deadline is the next marker, followed by the council’s published tally. In our view, a figure on this scale will make Chapelcross a test case for how Scottish planners weigh local objection against national ambitions for AI compute, especially if the forthcoming guidance arrives before councillors decide.