TL;DR
West Norfolk’s borough council, based in King’s Lynn, voted unanimously for a five-point response to the Longmarsh Green Energy project at an extraordinary meeting attended by about 350 people, the BBC reported on 17 November. The steps include writing to the Energy Secretary and pursuing legal challenges to the government’s eventual decision if warranted. The scheme would combine a large data centre with one of the UK’s biggest solar farms on 4,695 acres of farmland.
Around 200 of those present followed proceedings on a live stream shown in King’s Lynn Minster.
What the council decided
Because of its size, Longmarsh will be treated as a nationally significant infrastructure project, so ministers, not the borough, will decide it. The motion therefore focuses on influence. Councillors agreed to write to the Energy Secretary asking ministers to put local communities “at the heart” of such decisions, to work with neighbouring authorities on responses to large infrastructure schemes in West Norfolk, and to oppose renewable developments that lack local support and threaten farmland where appropriate.
They also want energy networks and distribution reviewed, and agreed to assess the final government decision and consider a legal challenge.
Farmland at the centre
Residents’ objections centred on lost farmland and what it means for food supply, and on why prime farmland was chosen over brownfield sites. Natural England rates the affected land grade one, a rating the BBC glosses as “excellent quality” agricultural land.
A Longmarsh spokesperson said the project would help build “a cleaner, lower cost and more secure energy system” and support everyday online services, from banking and streaming to NHS records and national defence. The developer is consulting until 26 November before submitting a development consent order application.
Looking forward
The developer expects to apply by April 2027. The Planning Inspectorate’s examination could take six months, so a decision could come by July 2028. The meeting follows a parish gathering on 2 November, when more than 400 people turned out. In our view, the notable step is a borough council formally keeping a legal challenge open well before the application has even been submitted, let alone examined.